Download the PDF

SAMPLE. Illustrative, anonymised data showing the format of a Weston weekly site report. Live reports also carry dated photos for every item.

Project Details

ItemDetails
ProjectG+4 residential building, New Town, Kolkata (sample)
Report no.14
PeriodWeek 14 of construction
ContractorCivil contractor (turnkey)
Weston site engineerNamed engineer, daily attendance
WeatherRain on 4 of 6 working days

1. Summary

  • Progress: 39% complete against 42% planned. The 3% slip is due to rain delaying the 2nd floor slab pour by two days.
  • Decision needed from owner: confirm the window frame specification before the end of next week to hold the finishing schedule.
  • Billing: running bill 5 verified. Recommended payment is 5.5% lower than claimed (see section 5).

2. Work Done This Week

ActivityLocationStatus
Slab and beam reinforcement2nd floorCompleted and inspected
Slab concreting, M25, 18 m³2nd floorPoured, curing started the same day
Brickwork, 125 mm and 250 mm walls1st floor70% complete
Internal plasterGround floorStarted, 15% complete
Plumbing sleeves and electrical conduits2nd floor slabFixed before pour, checked

3. Quality Checks

CheckResult
Pre-pour inspection, 2nd floor slabPassed after corrections: cover blocks added at 4 locations, chair spacing corrected, extra bars fixed at stair opening
Slump at pour90 mm against the specified 75 – 100 mm
Cube samples, 2nd floor slab3 samples (9 cubes) cast for 18 m³, per IS 456 clause 15.2.2
28-day cube results, 1st floor slab (M25)Sample means 31.8, 32.6 and 33.0 N/mm². Meets IS 456 acceptance criteria.
Curing log, 1st floor slabDay 10 of 10 completed (PPC)

4. Materials Received and Tested

MaterialQuantityCheck
PPC cement200 bagsManufacturing date within 30 days, stored on pallets
TMT Fe500D4.2 tonnesMill test certificate matched to lot; weight check within tolerance
River sand2 lorriesField silt test 5%, accepted

5. Running Bill Verification

ItemClaimedVerifiedDifference
Shuttering, 2nd floor slab and beams₹1,48,000₹1,31,200₹16,800 (area over-measured)
Brickwork, 1st floor₹2,16,500₹1,87,100₹29,400 (openings not deducted)
Other items₹4,78,000₹4,78,000—
Total₹8,42,500₹7,96,300₹46,200 (5.5%)

6. Open Issues and Non-Conformance Log

Ref.IssueActionStatus
NCR-07Honeycombing at column C4, ground floorRepair method approved by structural engineer and executedClosed
NCR-08Plaster thickness over 15 mm on one wall, ground floorContractor to rectify before tilingOpen
SAFE-03Edge protection missing at 2nd floor slab edgeTemporary barricade installed the same dayClosed

7. Look-Ahead: Next Two Weeks

  • 2nd floor columns: reinforcement inspection, then pour
  • Complete 1st floor brickwork
  • Order 3rd floor reinforcement steel against the bar bending schedule