Slump is the quickest check that the concrete arriving on site has the workability the pour needs. A slump far above specification usually means water was added, and that costs strength and durability.

The Procedure

  1. Use a standard slump cone: 300 mm high, 200 mm base diameter, 100 mm top diameter, on a flat, non-absorbent base.
  2. Fill in three layers of roughly equal height. Tamp each layer 25 times with a 16 mm rod.
  3. Strike off the top and lift the cone vertically and steadily, in about 5 to 10 seconds.
  4. Measure the drop from the top of the cone to the highest point of the concrete.

Reading the shape: a true slump subsides evenly and is valid. A shear slump (one side slides off) means repeat the test. A collapse means the mix is far too wet, unless it is a designed flowing concrete.

Workability Ranges (IS 456, Clause 7.1)

Placing conditionDegree of workabilitySlump (mm)
Blinding concrete, shallow sections, pavements using paversVery lowSee IS 456 clause 7.1.1
Mass concrete, lightly reinforced slabs, beams, walls, columns, floors, strip footingsLow25 – 75
Heavily reinforced slabs, beams, walls, columnsMedium50 – 100
Slipform work, pumped concreteMedium75 – 100
Trench fill, in-situ pilingHigh100 – 150
Tremie concreteVery highSee IS 456 clause 7.1.1

For bored cast-in-situ piles, IS 2911 (Part 1/Sec 2) specifies a tremie concrete slump of 150 to 180 mm at the time of pouring. See our pile foundation guide.

Site Rules We Enforce

  • The specified slump is written on the pour card before the pour starts
  • Slump is tested for the first load and at regular intervals, recorded against the cube samples
  • No water is added at site to raise slump. If workability is needed, it comes from the mix design and admixtures.

Reference

  • IS 456:2000, clause 7 (Workability of concrete)
  • IS 1199, Methods of sampling and analysis of concrete (slump test)
  • IS 2911 (Part 1/Sec 2):2010, clause 7.3

Summary for site use. Always work from the current edition of the standard and your project specification. Where they differ, the structural engineer’s specification governs.